Oct 23, 2019
LM on behalf of HS2 have confirmed that high volumes of rainfall and the poor condition of existing drainage in the area has resulted in programme delays. As such the current 24/7 single lane closures on the A446 and A452 will need to remain in place until 25...
Oct 11, 2019
LM on behalf of HS2 have provided us with the following information about single lane road closures from Monday 21 October to Wednesday 23 October. This will include overnight working (8pm to 6am) and daytime working (between 9.30am and 3.30pm). For full details...
Oct 11, 2019
LM on behalf of HS2 have provided us with the following information regarding works in our area. Works are due to commence on the 14th October:
May 3, 2019
Groundwork and environmental investigations are continuing to be carried out at various locations along the local route of HS2 with vegetation being cleared. Facilitation works are also underway with adaptions to existing roadways and the building of...
Apr 9, 2019
The Community Engagement Team for Balfour Beatty VINCI (on behalf of HS2) has been in touch to confirm that there are Ground Penetrating Radar (GPR) Survey Works planned in farm land situated off Diddington Lane in Hampton-in-Arden. Balfour Beatty VINCI will working...
Apr 4, 2019
We have received the following update leaflet from HS2 in regards to the establishment of a haul route for Berkswell (see below). The short note explains how Balfour Beatty Vinci will establish a continuous haul route in the Parish of Berkswell. The works will include...